School Rebuild Photo Roll Week 1829 June 2025 (by admin) |
Why not take a sneaky peak behind the rebuild fence with us!
During the last two weeks, the concrete on the ground floor has been completed, external wall panels have been added to the skeleton structure, and the first sheet layer of the roof has been completed. In the coming week the external walls will start to get some cladding (which will really start to make it look like a real building), and the roof will start to get its extra layers of insulation and protection from the elements. Once the cladding is on the outer walls, then the present scaffolding will be taken down.
Just follow the link and click on the attachment to see what progress has been made.
Keep your eyes peeled as we go through the weeks for more photos, as our new school continues to take shape!